Moglix Enables Fabrication of 5000 MT Structure, Raw Material Procurement & Painting for a Brownfield Capex Project in Hazira for the World's Largest Steel Maker

banner Image

Our Client

The project owner is the world's largest steel maker and is expanding its plant at Hazira, Gujarat from 9 MTPA to 15 MTPA. The L1 project developer for expansion of the steel plant is part of a salt-to-sky conglomerate and is one of India's largest EPC infrastructure companies. Moglix has provided 5000 MT fabrication, raw materials and painting for the project.

Business Challenges

  • Need for one-stop solution
  • QAP for procurement
  • Fabrication at EPC approved facility only
  • +/- 10% margin error allowed

5000 MT of Fabricated Structures Delivered in 12 Months

Solution

Explore how Moglix is providing capex project procurement solutions for expansion of a steel plant in Hazira